INTRODUCTION

Software Engineering Management can be defined as the
application of management activities—planning, coordinating, measuring,
monitoring, controlling, and reporting—to ensure that the development and
maintenance of software is systematic, disciplined, and quantified
(IEEE610.12-90).
The Software Engineering Management KA therefore
addresses the management and measurement of software engineering. While
measurement is an important aspect of all KAs, it is here that the topic of
measurement programs is presented.
While it is true to say that in one sense it should be
possible to manage software engineering in the same way as any other
(complex) process, there are aspects specific to software products and the
software life cycle processes which complicate effective management—just a
few of which are as follows:
-
The perception of
clients is such that there is often a lack of appreciation for the
complexity inherent in software engineering, particularly in relation to
the impact of changing requirements.
-
It is almost
inevitable that the software engineering processes themselves will
generate the need for new or changed client requirements.
-
As a result,
software is often built in an iterative process rather than a sequence
of closed tasks.
-
Software
engineering necessarily incorporates aspects of creativity and
discipline—maintaining an appropriate balance between the two is often
difficult.
-
The degree of
novelty and complexity of software is often extremely high.
-
There is a rapid
rate of change in the underlying technology.
With respect to software engineering, management
activities occur at three levels: organizational and infrastructure
management, project management, and measurement program planning and
control. The last two are covered in detail in this KA description. However,
this is not to diminish the importance of organizational management issues.
Since the link to the related disciplines—obviously
management—is important, it will be described in more detail than in the
other KA descriptions. Aspects of organizational management are important in
terms of their impact on software engineering—on policy management, for
instance: organizational policies and standards provide the framework in
which software engineering is undertaken. These policies may need to be
influenced by the requirements of effective software development and
maintenance, and a number of software engineering-specific policies may need
to be established for effective management of software engineering at an
organizational level. For example, policies are usually necessary to
establish specific organization-wide processes or procedures for such
software engineering tasks as designing, implementing, estimating, tracking,
and reporting. Such policies are essential to effective long-term software
engineering management, by establishing a consistent basis on which to
analyze past performance and implement improvements, for example.
Another important aspect of management is personnel
management: policies and procedures for hiring, training, and motivating
personnel and mentoring for career development are important not only at the
project level but also to the longer-term success of an organization.
Software engineering personnel may present unique training or personnel
management challenges (for example, maintaining currency in a context where
the underlying technology undergoes continuous and rapid change).
Communication management is also often mentioned as an overlooked but major
aspect of the performance of individuals in a field where precise
understanding of user needs and of complex requirements and designs is
necessary. Finally, portfolio management, which is the capacity to have an
overall vision not only of the set of software under development but also of
the software already in use in an organization, is necessary. Furthermore,
software reuse is a key factor in maintaining and improving productivity and
competitiveness. Effective reuse requires a strategic vision that reflects
the unique power and requirements of this technique.
In addition to understanding the aspects of management
that are uniquely influenced by software, software engineers must have some
knowledge of the more general aspects, even in the first four years after
graduation that is targeted in the Guide.
Organizational culture and behavior, and functional
enterprise management in terms of procurement, supply chain management,
marketing, sales, and distribution, all have an influence, albeit
indirectly, on an organization’s software engineering process.
Relevant to this KA is the notion of project management,
as “the construction of useful software artifacts” is normally managed in
the form of (perhaps programs of) individual projects. In this regard, we
find extensive support in the Guide to the Project Management Body of
Knowledge (PMBOK) (PMI00), which itself includes the following project
management KAs: project integration management, project scope management,
project time management, project cost management, project quality
management, project human resource management, and project communications
management. Clearly, all these topics have direct relevance to the Software
Engineering Management KA. To attempt to duplicate the content of the Guide
to the PMBOK here would be both impossible and inappropriate. Instead, we
suggest that the reader interested in project management beyond what is
specific to software engineering projects consult the PMBOK itself. Project
management is also found in the Related Disciplines of Software Engineering
chapter.
The Software Engineering Management KA consists of both
the software project management process, in its first five subareas, and
software engineering measurement in the last subarea. While these two
subjects are often regarded as being separate, and indeed they do possess
many unique aspects, their close relationship has led to their combined
treatment in this KA. Unfortunately, a common perception of the software
industry is that it delivers products late, over budget, and of poor quality
and uncertain functionality. Measurement-informed management — an assumed
principle of any true engineering discipline — can help to turn this
perception around. In essence, management without measurement, qualitative
and quantitative, suggests a lack of rigor, and measurement without
management suggests a lack of purpose or context. In the same way, however,
management and measurement without expert knowledge is equally ineffectual,
so we must be careful to avoid over-emphasizing the quantitative aspects of
Software Engineering Management (SEM). Effective management requires a
combination of both numbers and experience.
The following working definitions are adopted here:
-
Management process
refers
to the activities that are undertaken in order to ensure that the
software engineering processes are performed in a manner consistent with
the organization’s policies, goals, and standards.
-
Measurement
refers to the
assignment of values and labels to aspects of software engineering
(products, processes, and resources as defined by [Fen98]) and the
models that are derived from them, whether these models are developed
using statistical, expert knowledge or other techniques.
The software engineering project management subareas make
extensive use of the software engineering measurement subarea.
Not unexpectedly, this KA is closely related to others in
the Guide to the SWEBOK, and reading the following KA descriptions in
conjunction with this one would be particularly useful.
-
Software Requirements,
where some of the activities to be performed during the Initiation and
Scope definition phase of the project are described
-
Software Configuration Management,
as this deals with the
identification, control, status accounting, and audit of the software
configuration along with software release management and delivery
-
Software Engineering Process,
because processes and
projects are closely related (this KA also describes process and product
measurement)
-
Software Quality,
as quality is constantly
a goal of management and is an aim of many activities that must be
managed
BREAKDOWN OF TOPICS FOR SOFTWARE
ENGINEERING MANAGEMENT


Figure 1
Breakdown of topics for the Software Engineering Management KA
As the Software Engineering Management KA is viewed here
as an organizational process which incorporates the notion of process and
project management, we have created a breakdown that is both topic-based and
life cycle-based. However, the primary basis for the top-level breakdown is
the process of managing a software engineering project. There are six major
subareas. The first five subareas largely follow the IEEE/EIA 12207
Management Process. The six subareas are:
-
Initiation and scope definition,
which deals with the decision to initiate a software engineering project
-
Software project planning,
which addresses the activities undertaken to prepare for successful
software engineering from a management perspective
-
Software project enactment,
which deals with generally accepted software engineering management
activities that occur during software engineering
-
Review
and evaluation, which
deal with assurance that the software is satisfactory
-
Closure,
which addresses the post-completion activities of a software engineering
project
-
Software engineering measurement,
which deals with the effective development and implementation of
measurement programs in software engineering organizations
(IEEE12207.0-96)
The breakdown of topics for the Software Engineering
Management KA is shown in Figure 1.
1. Initiation and Scope Definition

The focus of this set of activities is on the
effective determination of software requirements via various
elicitation methods and the assessment of the project’s feasibility
from a variety of standpoints. Once feasibility has been
established, the remaining task within this process is the
specification of requirements validation and change procedures (see
also the Software Requirements KA).
1.1. Determination and Negotiation of
Requirements [Dor02: v2c4; Pfl01: c4; Pre04: c7; Som05: c5]
Software requirement methods for requirements
elicitation (for example, observation), analysis (for example, data
modeling, use-case modeling), specification, and validation (for
example, prototyping) must be selected and applied, taking into
account the various stakeholder perspectives. This leads to the
determination of project scope, objectives, and constraints. This is
always an important activity, as it sets the visible boundaries for
the set of tasks being undertaken, and is particularly so where the
novelty of the undertaking is high. Additional information can be
found in the Software Requirements KA.
1.2. Feasibility Analysis (Technical,
Operational, Financial, Social/Political)
[Pre04: c6; Som05: c6]
Software engineers must be assured that adequate
capability and resources are available in the form of people,
expertise, facilities, infrastructure, and support (either
internally or externally) to ensure that the project can be
successfully completed in a timely and cost-effective manner (using,
for example, a requirement-capability matrix). This often requires
some “ballpark” estimation of effort and cost based on appropriate
methods (for example, expert-informed analogy techniques).
1.3. Process for the Review and Revision of
Requirements

Given the inevitability of change, it is vital
that agreement among stakeholders is reached at this early point as
to the means by which scope and requirements are to be reviewed and
revised (for example, via agreed change management procedures). This
clearly implies that scope and requirements will not be “set in
stone” but can and should be revisited at predetermined points as
the process unfolds (for example, at design reviews, management
reviews). If changes are accepted, then some form of traceability
analysis and risk analysis (see topic 2.5
Risk Management)
should be used to ascertain the impact of those changes. A
managed-change approach should also be useful when it comes time to
review the outcome of the project, as the scope and requirements
should form the basis for the evaluation of success. [Som05: c6] See
also the software configuration control subarea of the Software
Configuration Management KA.
2. Software Project Planning

The iterative planning process is informed by the
scope and requirements and by the establishment of feasibility. At
this point, software life cycle processes are evaluated and the most
appropriate (given the nature of the project, its degree of novelty,
its functional and technical complexity, its quality requirements,
and so on) is selected. Where relevant, the project itself is then
planned in the form of a hierarchical decomposition of tasks, the
associated deliverables of each task are specified and characterized
in terms of quality and other attributes in line with stated
requirements, and detailed effort, schedule, and cost estimation is
undertaken. Resources are then allocated to tasks so as to optimize
personnel productivity (at individual, team, and organizational
levels), equipment and materials utilization, and adherence to
schedule. Detailed risk management is undertaken and the “risk
profile” of the project is discussed among, and accepted by, all
relevant stakeholders. Comprehensive software quality management
processes are determined as part of the planning process in the form
of procedures and responsibilities for software quality assurance,
verification and validation, reviews, and audits (see the Software
Quality KA). As an iterative process, it is vital that the processes
and responsibilities for ongoing plan management, review, and
revision are also clearly stated and agreed.
2.1. Process Planning

Selection of the appropriate software life cycle
model (for example, spiral, evolutionary prototyping) and the
adaptation and deployment of appropriate software life cycle
processes are undertaken in light of the particular scope and
requirements of the project. Relevant methods and tools are also
selected. [Dor02: v1c6,v2c8; Pfl01: c2; Pre04: c2; Rei02: c1,c3,c5;
Som05: c3; Tha97: c3] At the project level, appropriate methods and
tools are used to decompose the project into tasks, with associated
inputs, outputs, and completion conditions (for example, work
breakdown structure). [Dor02: v2c7; Pfl01: c3; Pre04: c21; Rei02:
c4,c5; Som05: c4; Tha97: c4,c6] This in turn influences decisions on
the project’s high-level schedule and organization structure.
2.2. Determine Deliverables

The product(s) of each task (for example,
architectural design, inspection report) are specified and
characterized. [Pfl01: c3; Pre04: c24; Tha97: c4] Opportunities to
reuse software components from previous developments or to utilize
off-the-shelf software products are evaluated. Use of third parties
and procured software are planned and suppliers are selected.
2.3. Effort, Schedule, and Cost Estimation

Based on the breakdown of tasks, inputs, and
outputs, the expected effort range required for each task is
determined using a calibrated estimation model based on historical
size-effort data where available and relevant, or other methods like
expert judgment. Task dependencies are established and potential
bottlenecks are identified using suitable methods (for example,
critical path analysis). Bottlenecks are resolved where possible,
and the expected schedule of tasks with projected start times,
durations, and end times is produced (for example, PERT chart).
Resource requirements (people, tools) are translated into cost
estimates. [Dor02: v2c7; Fen98: c12; Pfl01: c3; Pre04: c23, c24;
Rei02: c5,c6; Som05: c4,c23; Tha97: c5] This is a highly iterative
activity which must be negotiated and revised until consensus is
reached among affected stakeholders (primarily engineering and
management).
2.4. Resource Allocation
[Pfl01: c3; Pre04: c24; Rei02:
c8,c9; Som05: c4; Tha97: c6,c7]
Equipment, facilities, and people are associated
with the scheduled tasks, including the allocation of
responsibilities for completion (using, for example, a Gantt chart).
This activity is informed and constrained by the availability of
resources and their optimal use under these circumstances, as well
as by issues relating to personnel (for example, productivity of
individuals/teams, team dynamics, organizational and team
structures).
2.5. Risk Management

Risk identification and analysis (what can go
wrong, how and why, and what are the likely consequences), critical
risk assessment (which are the most significant risks in terms of
exposure, which can we do something about in terms of leverage),
risk mitigation and contingency planning (formulating a strategy to
deal with risks and to manage the risk profile) are all undertaken.
Risk assessment methods (for example, decision trees and process
simulations) should be used in order to highlight and evaluate
risks. Project abandonment policies should also be determined at
this point in discussion with all other stakeholders. [Dor02: v2c7;
Pfl01: c3; Pre04: c25; Rei02: c11; Som05: c4; Tha97: c4]
Software-unique aspects of risk, such as software engineers’
tendency to add unwanted features or the risks attendant in
software’s intangible nature, must influence the project’s risk
management.
2.6. Quality Management
[Dor02: v1c8,v2c3-c5; Pre04:
c26; Rei02: c10; Som05: c24,c25; Tha97: c9,c10]

Quality is defined in terms of pertinent
attributes of the specific project and any associated product(s),
perhaps in both quantitative and qualitative terms. These quality
characteristics will have been determined in the specification of
detailed software requirements. See also the Software Requirements
KA.
Thresholds for adherence to quality are set for
each indicator as appropriate to stakeholder expectations for the
software at hand. Procedures relating to ongoing SQA throughout the
process and for product (deliverable) verification and validation
are also specified at this stage (for example, technical reviews and
inspections) (see also the Software Quality KA).
2.7. Plan Management
[Som05: c4; Tha97: c4]
How the project will be managed and how the plan
will be managed must also be planned. Reporting, monitoring, and
control of the project must fit the selected software engineering
process and the realities of the project, and must be reflected in
the various artifacts that will be used for managing it. But, in an
environment where change is an expectation rather than a shock, it
is vital that plans are themselves managed. This requires that
adherence to plans be systematically directed, monitored, reviewed,
reported, and, where appropriate, revised. Plans associated with
other management-oriented support processes (for example,
documentation, software configuration management, and problem
resolution) also need to be managed in the same manner.
3. Software Project Enactment

The plans are then implemented, and the processes
embodied in the plans are enacted. Throughout, there is a focus on
adherence to the plans, with an overriding expectation that such
adherence will lead to the successful satisfaction of stakeholder
requirements and achievement of the project objectives. Fundamental
to enactment are the ongoing management activities of measuring,
monitoring, controlling, and reporting.
3.1. Implementation of Plans
[Pfl01: c3; Som05: c4]

The project is initiated and the project
activities are undertaken according to the schedule. In the process,
resources are utilized (for example, personnel effort, funding) and
deliverables are produced (for example, architectural design
documents, test cases).
3.2. Supplier Contract Management
[Som05:c4]

Prepare and execute agreements with suppliers,
monitor supplier performance, and accept supplier products,
incorporating them as appropriate.
3.3. Implementation of measurement process
[Fen98: c13,c14;
Pre04: c22; Rei02: c10,c12; Tha97: c3,c10]
The measurement process is enacted alongside the
software project, ensuring that relevant and useful data are
collected (see also topics 6.2
Plan the Measurement
Process and 6.3
Perform the Measurement Process).
3.4. Monitor Process
[Dor02: v1c8, v2c2-c5,c7; Rei02:
c10; Som05: c25; Tha97: c3;c9]
Adherence to the various plans is assessed
continually and at predetermined intervals. Outputs and completion
conditions for each task are analyzed. Deliverables are evaluated in
terms of their required characteristics (for example, via reviews
and audits). Effort expenditure, schedule adherence, and costs to
date are investigated, and resource usage is examined. The project
risk profile is revisited, and adherence to quality requirements is
evaluated.
Measurement data are modeled and analyzed.
Variance analysis based on the deviation of actual from expected
outcomes and values is undertaken. This may be in the form of cost
overruns, schedule slippage, and the like. Outlier identification
and analysis of quality and other measurement data are performed
(for example, defect density analysis). Risk exposure and leverage
are recalculated, and decisions trees, simulations, and so on are
rerun in the light of new data. These activities enable problem
detection and exception identification based on exceeded thresholds.
Outcomes are reported as needed and certainly where acceptable
thresholds are surpassed.
3.5. Control Process
[Dor02: v2c7; Rei02: c10; Tha97:
c3,c9]
The outcomes of the process monitoring activities
provide the basis on which action decisions are taken. Where
appropriate, and where the impact and associated risks are modeled
and managed, changes can be made to the project. This may take the
form of corrective action (for example, retesting certain
components), it may involve the incorporation of contingencies so
that similar occurrences are avoided (for example, the decision to
use prototyping to assist in software requirements validation),
and/or it may entail the revision of the various plans and other
project documents (for example, requirements specification) to
accommodate the unexpected outcomes and their implications.
In some instances, it may lead to abandonment of
the project. In all cases, change control and software configuration
management procedures are adhered to (see also the Software
Configuration Management KA), decisions are documented and
communicated to all relevant parties, plans are revisited and
revised where necessary, and relevant data is recorded in the
central database (see also topic 6.3
Perform the
Measurement Process).
3.6. Reporting
[Rei02: c10; Tha97: c3,c10]
At specified and agreed periods, adherence to the
plans is reported, both within the organization (for example to the
project portfolio steering committee) and to external stakeholders
(for example, clients, users). Reports of this nature should focus
on overall adherence as opposed to the detailed reporting required
frequently within the project team.
4. Review and Evaluation

At critical points in the project, overall
progress towards achievement of the stated objectives and
satisfaction of stakeholder requirements are evaluated. Similarly,
assessments of the effectiveness of the overall process to date, the
personnel involved, and the tools and methods employed are also
undertaken at particular milestones.
4.1. Determining Satisfaction of Requirements
[Rei02: c10;
Tha97: c3,c10]
Since attaining stakeholder (user and customer)
satisfaction is one of our principal aims, it is important that
progress towards this aim be formally and periodically assessed.
This occurs on achievement of major project milestones (for example,
confirmation of software design architecture, software integration
technical review). Variances from expectations are identified and
appropriate action is taken. As in the control process activity
above (see topic 3.5
Control Process), in
all cases change control and software configuration management
procedures are adhered to (see the Software Configuration Management
KA), decisions are documented and communicated to all relevant
parties, plans are revisited and revised where necessary, and
relevant data are recorded in the central database (see also topic
6.3 Perform the
Measurement Process).
More information can also be found in the Software Testing KA, in
topic 2.2 Objectives of Testing
and in the Software Quality KA,
in topic 2.3 Reviews and Audits.
4.2. Reviewing and Evaluating Performance
[Dor02: v1c8,v2c3,c5;
Pfl01: c8,c9; Rei02: c10; Tha97: c3,c10]
Periodic performance reviews for project
personnel provide insights as to the likelihood of adherence to
plans as well as possible areas of difficulty (for example, team
member conflicts). The various methods, tools, and techniques
employed are evaluated for their effectiveness and appropriateness,
and the process itself is systematically and periodically assessed
for its relevance, utility, and efficacy in the project context.
Where appropriate, changes are made and managed.
5. Closure

The project reaches closure when all the plans
and embodied processes have been enacted and completed. At this
stage, the criteria for project success are revisited. Once closure
is established, archival, post mortem, and process improvement
activities are performed.
5.1. Determining Closure
[Dor02: v1c8,v2c3,c5; Rei02:
c10; Tha97: c3,c10]

The tasks as specified in the plans are complete,
and satisfactory achievement of completion criteria is confirmed.
All planned products have been delivered with acceptable
characteristics. Requirements are checked off and confirmed as
satisfied, and the objectives of the project have been achieved.
These processes generally involve all stakeholders and result in the
documentation of client acceptance and any remaining known problem
reports.
5.2. Closure Activities
[Pfl01: c12; Som05: c4]
After closure has been confirmed, archival of
project materials takes place in line with stakeholder-agreed
methods, location, and duration. The organization’s measurement
database is updated with final project data and post-project
analyses are undertaken. A project post mortem is undertaken so that
issues, problems, and opportunities encountered during the process
(particularly via review and evaluation, see subarea 4
Review and evaluation)
are analyzed, and lessons are drawn from the process and fed into
organizational learning and improvement endeavors (see also the
Software Engineering Process KA).
6. Software Engineering Measurement
[ISO 15939-02]
The importance of measurement and its role in
better management practices is widely acknowledged, and so its
importance can only increase in the coming years. Effective
measurement has become one of the cornerstones of organizational
maturity.
Key terms on software measures and measurement
methods have been defined in [ISO15939-02] on the basis of the ISO
international vocabulary of metrology [ISO93]. Nevertheless, readers
will encounter terminology differences in the literature; for
example, the term “metrics” is sometimes used in place of
“measures.”
This topic follows the international standard
ISO/IEC 15939, which describes a process which defines the
activities and tasks necessary to implement a software measurement
process and includes, as well, a measurement information model.
6.1. Establish and Sustain Measurement
Commitment

-
Accept
requirements for measurement.
Each
measurement endeavor should be guided by organizational
objectives and driven by a set of measurement requirements
established by the organization and the project. For example, an
organizational objective might be “first-to-market with new
products.” [Fen98: c3,c13; Pre04: c22] This in turn might
engender a requirement that factors contributing to this
objective be measured so that projects might be managed to meet
this objective.
-
Define scope of measurement.
The
organizational unit to which each measurement requirement is
to be applied must be established. This may consist of a
functional area, a single project, a single site, or even
the whole enterprise. All subsequent measurement tasks
related to this requirement should be within the defined
scope. In addition, the stakeholders should be identified.
-
Commitment of management and staff to
measurement. The commitment must be formally established,
communicated, and supported by resources (see next item).
-
Commit
resources for measurement. The organization’s commitment to
measurement is an essential factor for success, as evidenced by
assignment of resources for implementing the measurement
process. Assigning resources includes allocation of
responsibility for the various tasks of the measurement process
(such as user, analyst, and librarian) and providing adequate
funding, training, tools, and support to conduct the process in
an enduring fashion.
6.2. Plan the Measurement Process

-
Characterize the organizational unit. The organizational unit
provides the context for measurement, so it is important to make
this context explicit and to articulate the assumptions that it
embodies and the constraints that it imposes. Characterization
can be in terms of organizational processes, application
domains, technology, and organizational interfaces. An
organizational process model is also typically an element of the
organizational unit characterization [ISO15939-02: 5.2.1].
-
Identify
information needs. Information needs are based on the goals,
constraints, risks, and problems of the organizational unit.
They may be derived from business, organizational, regulatory,
and/or product objectives. They must be identified and
prioritized. Then, a subset to be addressed must be selected and
the results documented, communicated, and reviewed by
stakeholders [ISO 15939-02: 5.2.2].
-
Select
measures. Candidate measures must be selected, with clear links
to the information needs. Measures must then be selected based
on the priorities of the information needs and other criteria
such as cost of collection, degree of process disruption during
collection, ease of analysis, ease of obtaining accurate,
consistent data, and so on [ISO15939-02: 5.2.3 and Appendix C].
-
Define
data collection, analysis, and reporting procedures. This
encompasses collection procedures and schedules, storage,
verification, analysis, reporting, and configuration management
of data [ISO15939-02: 5.2.4].
-
Define
criteria for evaluating the information products. Criteria for
evaluation are influenced by the technical and business
objectives of the organizational unit. Information products
include those associated with the product being produced, as
well as those associated with the processes being used to manage
and measure the project [ISO15939-02: 5.2.5 and Appendices D,
E].
-
Review,
approve, and provide resources for measurement tasks.
-
The measurement plan must be reviewed and
approved by the appropriate stakeholders. This includes all
data collection procedures, storage, analysis, and reporting
procedures; evaluation criteria; schedules; and
responsibilities. Criteria for reviewing these artifacts
should have been established at the organizational unit
level or higher and should be used as the basis for these
reviews. Such criteria should take into consideration
previous experience, availability of resources, and
potential disruptions to projects when changes from current
practices are proposed. Approval demonstrates commitment to
the measurement process [ISO15939-02: 5.2.6.1 and Appendix
F.
-
Resources should be made available for
implementing the planned and approved measurement tasks.
Resource availability may be staged in cases where changes
are to be piloted before widespread deployment.
Consideration should be paid to the resources necessary for
successful deployment of new procedures or measures
[ISO15939-02: 5.2.6.2].
-
Acquire
and deploy supporting technologies. This includes evaluation of
available supporting technologies, selection of the most
appropriate technologies, acquisition of those technologies, and
deployment of those technologies [ISO 15939-02: 5.2.7].
6.3. Perform the Measurement Process

-
Integrate
measurement procedures with relevant processes. The measurement
procedures, such as data collection, must be integrated into the
processes they are measuring. This may involve changing current
processes to accommodate data collection or generation
activities. It may also involve analysis of current processes to
minimize additional effort and evaluation of the effect on
employees to ensure that the measurement procedures will be
accepted. Morale issues and other human factors need to be
considered. In addition, the measurement procedures must be
communicated to those providing the data, training may need to
be provided, and support must typically be provided. Data
analysis and reporting procedures must typically be integrated
into organizational and/or project processes in a similar manner
[ISO 15939-02: 5.3.1].
-
Collect
data. The data must be collected, verified, and stored [ISO
15939-02 :5.3.2].
-
Analyze
data and develop information products. Data may be aggregated,
transformed, or recoded as part of the analysis process, using a
degree of rigor appropriate to the nature of the data and the
information needs. The results of this analysis are typically
indicators such as graphs, numbers, or other indications that
must be interpreted, resulting in initial conclusions to be
presented to stakeholders. The results and conclusions must be
reviewed, using a process defined by the organization (which may
be formal or informal). Data providers and measurement users
should participate in reviewing the data to ensure that they are
meaningful and accurate, and that they can result in reasonable
actions [ISO 15939-02: 5.3.3 and Appendix G].
-
Communicate results. Information products must be documented and
communicated to users and stakeholders [ISO 15939-02: 5.3.4].
6.4. Evaluate Measurement

-
Evaluate
information products. Evaluate information products against
specified evaluation criteria and determine strengths and
weaknesses of the information products. This may be performed by
an internal process or an external audit and should include
feedback from measurement users. Record lessons learned in an
appropriate database [ISO 15939-02: 5.4.1 and Appendix D].
-
Evaluate
the measurement process. Evaluate the measurement process
against specified evaluation criteria and determine the
strengths and weaknesses of the process. This may be performed
by an internal process or an external audit and should include
feedback from measurement users. Record lessons learned in an
appropriate database [ISO 15939-02: 5.4.1 and Appendix D].
-
Identify
potential improvements. Such improvements may be changes in the
format of indicators, changes in units measured, or
reclassification of categories. Determine the costs and benefits
of potential improvements and select appropriate improvement
actions. Communicate proposed improvements to the measurement
process owner and stakeholders for review and approval. Also
communicate lack of potential improvements if the analysis fails
to identify improvements [ISO 15939-02: 5.4.2].
MATRIX OF TOPICS VS. REFERENCE MATERIAL


RECOMMENDED REFERENCES FOR SOFTWARE
ENGINEERING MANAGEMENT

-
[Dor02] M. Dorfman and R.H. Thayer, eds.,
Software
Engineering, IEEE
Computer Society Press, 2002, Vol. 1, Chap. 6, 8, Vol. 2, Chap.
3, 4, 5, 7, 8.
-
[Fen98] N.E. Fenton and S.L. Pfleeger,
Software Metrics:
A Rigorous & Practical Approach,
second ed., International Thomson Computer Press, 1998, Chap.
1-14.
-
[ISO15939-02] ISO/IEC 15939:2002,
Software
Engineering — Software Measurement Process,
ISO and IEC, 2002.
-
[Pfl01] S.L. Pfleeger,
Software
Engineering: Theory and Practice,
second ed., Prentice Hall, 2001, Chap. 2-4, 8, 9, 12, 13.
-
[Pre04] R.S. Pressman,
Software
Engineering: A Practitioner's Approach,
sixth ed., McGraw-Hill, 2004, Chap. 2, 6, 7, 22-26.
-
[Rei02] D.J. Reifer, ed.,
Software
Management, IEEE
Computer Society Press, 2002, Chap. 1-6, 7-12, 13.
-
[Som05] I. Sommerville,
Software
Engineering,
seventh ed., Addison-Wesley, 2005, Chap. 3-6, 23-25.
-
[Tha97] R.H. Thayer, ed.,
Software
Engineering Project Management,
IEEE Computer Society Press, 1997, Chap. 1-10.
APPENDIX A. LIST OF FURTHER READINGS

-
(Adl99) T.R. Adler, J.G. Leonard, and R.K.
Nordgren, “Improving Risk Management: Moving from Risk
Elimination to Risk Avoidance,”
Information and
Software Technology,
vol. 41, 1999, pp. 29-34.
-
(Bai98) R. Baines, “Across Disciplines: Risk,
Design, Method, Process, and Tools,”
IEEE Software,
July/August 1998, pp. 61-64.
-
(Bin97) R.V. Binder, “Can a Manufacturing
Quality Model Work for Software?”
IEEE Software,
September/October 1997, pp. 101-102,105.
-
(Boe97) B.W. Boehm and T. DeMarco, “Software
Risk Management,” IEEE Software,
May/June 1997, pp. 17-19.
-
(Bri96) L.C. Briand, S. Morasca, and V.R.
Basili, “Property-Based Software Engineering Measurement,”
IEEE Transactions on Software Engineering,
vol. 22, iss. 1, 1996, pp. 68-86.
-
(Bri96a) L. Briand, K.E. Emam, and S. Morasca,
“On the Application of Measurement Theory in Software
Engineering,” Empirical Software Engineering,
vol. 1, 1996, pp. 61-88.
-
(Bri97) L.C. Briand, S. Morasca, and V.R.
Basili, “Response to: Comments on ‘Property-based Software
Engineering Measurement: Refining the Addivity Properties,’”
IEEE
Transactions on Software Engineering,
vol. 23, iss. 3, 1997, pp. 196-197.
-
(Bro87) F.P.J. Brooks, “No Silver Bullet:
Essence and Accidents of Software Engineering,”
Computer,
Apr. 1987, pp. 10-19.
-
(Cap96) J. Capers,
Applied Software
Measurement: Assuring Productivity and Quality,
second ed., McGraw-Hill, 1996.
-
(Car97) M.J. Carr, “Risk Management May Not
Be For Everyone,” IEEE Software,
May/June 1997, pp. 21-24.
-
(Cha96) R.N. Charette, “Large-Scale Project
Management Is Risk Management,”
IEEE Software,
July 1996, pp. 110-117.
-
(Cha97) R.N. Charette, K.M. Adams, and M.B.
White, “Managing Risk in Software Maintenance,”
IEEE Software,
May/June 1997, pp. 43-50.
-
(Col96) B. Collier, T. DeMarco,and P. Fearey,
“A Defined Process for Project Postmortem Review,”
IEEE Software,
July 1996, pp. 65-72.
-
(Con97) E.H. Conrow and P.S. Shishido,
“Implementing Risk Management on Software Intensive Projects,”
IEEE
Software,
May/June 1997, pp. 83-89.
-
(Dav98) A.M. Davis, “Predictions and
Farewells,” IEEE Software,
July/August 1998, pp. 6-9.
-
(Dem87)
T. DeMarco and T. Lister,
Peopleware:
Productive Projects and Teams,
Dorset House Publishing, 1987.
-
(Dem96) T. DeMarco and A. Miller, “Managing
Large Software Projects,”
IEEE Software,
July 1996, pp. 24-27.
-
(Fav98) J. Favaro and S.L. Pfleeger, “Making
Software Development Investment Decisions,”
ACM SIGSoft
Software Engineering Notes,
vol. 23, iss. 5, 1998, pp. 69-74.
-
(Fay96) M.E. Fayad and M. Cline, “Managing
Object-Oriented Software Development,”
Computer,
September 1996, pp. 26-31.
-
(Fen98) N.E. Fenton and S.L. Pfleeger,
Software Metrics:
A Rigorous & Practical Approach,
second ed., International Thomson Computer Press, 1998.
-
(Fle99) R. Fleming, “A Fresh Perspective on
Old Problems,” IEEE Software,
January/February 1999, pp. 106-113.
-
(Fug98) A. Fuggetta et al., “Applying GQM in
an Industrial Software Factory,”
ACM Transactions
on Software Engineering and Methodology,
vol. 7, iss. 4, 1998, pp. 411-448.
-
(Gar97) P.R. Garvey, D.J. Phair, and J.A.
Wilson, “An Information Architecture for Risk Assessment and
Management,” IEEE Software,
May/June 1997, pp. 25-34.
-
(Gem97) A. Gemmer, “Risk Management: Moving
beyond Process,” Computer,
May 1997, pp. 33-43.
-
(Gla97) R.L. Glass, “The Ups and Downs of
Programmer Stress,” Communications of
the ACM, vol. 40,
iss. 4, 1997, pp. 17-19.
-
(Gla98) R.L. Glass, “Short-Term and Long-Term
Remedies for Runaway Projects,”
Communications of
the ACM, vol. 41,
iss. 7, 1998, pp. 13-15.
-
(Gla98a) R.L. Glass, “How Not to Prepare for
a Consulting Assignment, and Other Ugly Consultancy Truths,”
Communications of the ACM,
vol. 41, iss. 12, 1998, pp. 11-13.
-
(Gla99) R.L. Glass, “The Realities of
Software Technology Payoffs,”
Communications of
the ACM, vol. 42,
iss. 2, 1999, pp. 74-79.
-
(Gra99) R. Grable et al., “Metrics for Small
Projects: Experiences at the SED,”
IEEE Software,
March/April 1999, pp. 21-29.
-
(Gra87) R.B. Grady and D.L. Caswell,
Software Metrics:
Establishing A Company-Wide Program.
Prentice Hall, 1987.
-
(Hal97) T. Hall and N. Fenton, “Implementing
Effective Software Metrics Programs,”
IEEE Software,
March/April 1997, pp. 55-64.
-
(Hen99) S.M. Henry and K.T. Stevens, “Using
Belbin’s Leadership Role to Improve Team Effectiveness: An
Empirical Investigation,”
Journal of Systems
and Software,
vol. 44, 1999, pp. 241-250.
-
(Hoh99)
L. Hohmann, “Coaching the Rookie Manager,”
IEEE Software,
January/February 1999, pp. 16-19.
-
(Hsi96)
P. Hsia, “Making Software Development Visible,”
IEEE Software,
March 1996, pp. 23-26.
-
(Hum97) W.S. Humphrey,
Managing Technical
People: Innovation, Teamwork, and the Software Process:
Addison-Wesley, 1997.
-
(IEEE12207.0-96) IEEE/EIA
12207.0-1996//ISO/IEC12207:1995,
Industry
Implementation of Int. Std. ISO/IEC 12207:95, Standard for
Information Technology-Software Life Cycle Processes,
IEEE, 1996.
-
(Jac98) M. Jackman, “Homeopathic Remedies for
Team Toxicity,” IEEE Software,
July/August 1998, pp. 43-45.
-
(Kan97) K. Kansala, “Integrating Risk
Assessment with Cost Estimation,”
IEEE Software,
May/June 1997, pp. 61-67.
-
(Kar97) J. Karlsson and K. Ryan, “A
Cost-Value Aproach for Prioritizing Requirements,”
IEEE Software,
September/October 1997, pp. 87-74.
-
(Kar96) D.W. Karolak,
Software
Engineering Risk Management,
IEEE Computer Society Press, 1996.
-
(Kau99) K. Kautz, “Making Sense of
Measurement for Small Organizations,”
IEEE Software,
March/April 1999, pp. 14-20.
-
(Kei98) M. Keil et al., “A Framework for
Identifying Software Project Risks,”
Communications of
the ACM, vol. 41,
iss. 11, 1998, pp. 76-83.
-
(Ker99) B. Kernighan and R. Pike, “Finding
Performance Improvements,”
IEEE Software,
March/April 1999, pp. 61-65.
-
(Kit97) B. Kitchenham and S. Linkman,
“Estimates, Uncertainty, and Risk,”
IEEE Software,
May/June 1997, pp. 69-74.
-
(Lat98) F. v. Latum et al., “Adopting GQM-Based
Measurement in an Industrial Environment,”
IEEE Software,
January-February 1998, pp. 78-86.
-
(Leu96) H.K.N. Leung, “A Risk Index for
Software Producers,” Software
Maintenance: Research and Practice,
vol. 8, 1996, pp. 281-294.
-
(Lis97) T. Lister, “Risk Management Is
Project Management for Adults,”
IEEE Software,
May/June 1997, pp. 20-22.
-
(Mac96) K. Mackey, “Why Bad Things Happen to
Good Projects,” IEEE Software,
May 1996, pp. 27-32.
-
(Mac98) K. Mackey, “Beyond Dilbert: Creating
Cultures that Work,” IEEE Software,
January/February 1998, pp. 48-49.
-
(Mad97) R.J. Madachy, “Heuristic Risk
Assessment Using Cost Factors,”
IEEE Software,
May/June 1997, pp. 51-59.
-
(McC96) S.C. McConnell,
Rapid Development:
Taming Wild Software Schedules,
Microsoft Press, 1996.
-
(McC97) S.C. McConnell,
Software Project
Survival Guide,
Microsoft Press, 1997.
-
(McC99) S.C. McConnell, “Software Engineering
Principles,” IEEE Software,
March/April 1999, pp. 6-8.
-
(Moy97) T. Moynihan, “How Experienced Project
Managers Assess Risk,”
IEEE Software,
May/June 1997, pp. 35-41.
-
(Ncs98) P. Ncsi, “Managing OO Projects
Better,” IEEE Software,
July/August 1998, pp. 50-60.
-
(Nol99) A.J. Nolan, “Learning From Success,”
IEEE
Software,
January/February 1999, pp. 97-105.
-
(Off97) R.J. Offen and R. Jeffery,
“Establishing Software Measurement Programs,”
IEEE Software,
March/April 1997, pp. 45-53.
-
(Par96) K.V.C. Parris, “Implementing
Accountability,”
IEEE Software,
July/August 1996, pp. 83-93.
-
(Pfl97) S.L. Pfleeger, “Assessing Measurement
(Guest Editor’s Introduction),”
IEEE Software,
March/April 1997, pp. 25-26.
-
(Pfl97a) S.L. Pfleeger et al., “Status Report
on Software Measurement,”
IEEE Software,
March/April 1997, pp. 33-43.
-
(Put97) L.H. Putman and W. Myers,
Industrial
Strength Software — Effective Management Using Measurement,
IEEE Computer Society Press, 1997.
-
(Rob99) P.N. Robillard, “The Role of
Knowledge in Software Development,”
Communications of
the ACM, vol. 42,
iss. 1, 1999, pp. 87-92.
-
(Rod97) A.G. Rodrigues and T.M. Williams,
“System Dynamics in Software Project Management: Towards the
Development of a Formal Integrated Framework,”
European Journal of Information Systems,
vol. 6, 1997, pp. 51-66.
-
(Rop97) J. Ropponen and K. Lyytinen, “Can
Software Risk Management Improve System Development: An
Exploratory Study,” European Journal
of Information Systems,
vol. 6, 1997, pp. 41-50.
-
(Sch99) C. Schmidt et al., “Disincentives for
Communicating Risk: A Risk Paradox,”
Information and
Software Technology,
vol. 41, 1999, pp. 403-411.
-
(Sco92) R.L. v. Scoy, “Software Development
Risk: Opportunity, Not Problem,” Software Engineering Institute,
Carnegie Mellon University CMU/SEI-92-TR-30, 1992.
-
(Sla98) S.A. Slaughter, D.E. Harter, and M.S.
Krishnan, “Evaluating the Cost of Software Quality,”
Communications of the ACM,
vol. 41, iss. 8, 1998, pp. 67-73.
-
(Sol98) R. v. Solingen, R. Berghout, and F.
v. Latum, “Interrupts: Just a Minute Never Is,”
IEEE Software,
September/October 1998, pp. 97-103.
-
(Whi95) N. Whitten,
Managing Software
Development Projects: Formulas for Success,
Wiley, 1995.
-
(Wil99) B. Wiley,
Essential System
Requirements: A Practical Guide to Event-Driven Methods,
Addison-Wesley, 1999.
-
(Zel98) M.V. Zelkowitz and D.R. Wallace,
“Experimental Models for Validating Technology,”
Computer,
vol. 31, iss. 5, 1998, pp. 23-31.
A PPENDIX
B. LIST
OF STANDARDS
-
(IEEE610.12-90) IEEE Std 610.12-1990 (R2002),
IEEE
Standard Glossary of Software Engineering Terminology,
IEEE, 1990.
-
(IEEE12207.0-96) IEEE/EIA
12207.0-1996//ISO/IEC12207:1995,
Industry
Implementation of Int. Std. ISO/IEC 12207:95, Standard for
Information Technology-Software Life Cycle Processes,
IEEE, 1996.
-
(ISO15939-02) ISO/IEC 15939:2002,
Software
Engineering-Software Measurement Process,